Drilling derricks and Rig Masts consist of a steel framework with a square or rectangular cross-section. Their purpose is to support the hoisting equipment and rack the tubulars while tripping pipe. The number of joints in a stand (single-double-triple) that the rig can pull is dependent on the height of the derrick. .
The Drawworks is one of the most important components of the drilling rig (types of drilling rigs). The unit supplies the hoisting power, the. .
The Crown Blockas a drilling rig component is a fixed set of pulleys (called sheaves) located at the top of the derrick or mast, where the drilling line is threaded. The companion blocks to these pulleys are the traveling blocks. By using two sets of blocks in this fashion,. .
The Traveling Blockis a set of sheaves (pulleys) that move up and down in the derrick. The drilling line is threaded (reeved) over the. .
Attached to the bottom of the traveling blocks, the hook is required to hang the swivel and rig kelly(for drilling) and the elevator bales (for tripping pipe and casing).
[pdf] Directional drilling (or slant drilling) is the practice of drilling non-vertical bores. It can be broken down into four main groups: oilfield directional drilling, utility installation directional drilling, directional boring (horizontal directional drilling - HDD), and surface in seam (SIS), which horizontally intersects a vertical bore target to extract coal bed methane.. HistoryMany prerequisites enabled this suite of technologies to become productive. Probably, the first requirement was the realization that , or , do not necessarily need to be vertical. This realization. .
Wells are drilled directionally for several purposes: • Increasing the exposed section length through the reservoir by drilling through the reservoir at an angle.• Drilling into the reservoir w.
[pdf] 
Many accidents on the drill floorwhile pipe tripping involve using tongs. Injuries result from being caught between tongs and being struck by swinging tongs. All tongs should be securely attached and anchored. Tong safety lines should be of sufficient length, preferably allowing a 90° breakout angle between the. .
Ensure that the crew is up to strength and that individuals know the tasks to be carried out. A communication system should be operational between. .
Considerable preparation is required before the trip is commenced. The following are among the most essential actions that should be carried out. .
Having completed the preparations outlined in the previous section, the trip out of the hole can be started. The following procedure is proposed as a guideline: 1. Flow checkthe well with the pumps off to ensure that the well is static. 1. Pump a slug. This enables the pipe to be pulled dry and the hole to be accurately monitored during a trip. 2. . The underground pipe drilling machine, also named horiztontal directional drilling machine, is a piece of equipment specifically designed to drill holes or tunnels underground to install pipelines. It quickly drills holes in the ground by drilling to lay pipes underground.
[pdf]