The mast is normally used on land drilling rig types requiring a good deal of mobility; they are rarely used on offshore rigs. The racking board is in a cantilever position and lengths of drill pipeare racked on a floor, called the setback, that is separate from the mast structure. Most masts have one side open (window side),. .
There are different types of masts for land drilling and service rigs: 1. Folding Type 2. Telescopic Masts 3. Bootstrap Type 4. Portable/Cantilivered masts (Non-Guy line) .
Figure 8 shows a telescopic mast. Telescopic masts with their drawworks and engines are usually mounted on trucks or trailers. The load should be borne by hydraulic or. .
Each structure shall be rated for the following applicable loading conditions. The following ratings do not include any allowance for impact. Acceleration, impact, setback, and wind loads will reduce the rated static hook load capacity. Technical specifications are identical to those for derricks: 1. Maximum hook load given the reeving system, 2. F. .
For conventional Mast (Land rig), the below pictures show the erection sequence of rigging up For rigging up the vertical mast, the below pictures show the bootstrap sequence of rigging up.
[pdf] 
The mast is normally used on land drilling rig types requiring a good deal of mobility; they are rarely used on offshore rigs. The racking board is in a cantilever position and lengths of drill pipeare racked on a floor, called the setback, that is separate from the mast structure. Most masts have one side open (window side),. .
There are different types of masts for land drilling and service rigs: 1. Folding Type 2. Telescopic Masts 3. Bootstrap Type 4. Portable/Cantilivered masts (Non-Guy line) .
Figure 8 shows a telescopic mast. Telescopic masts with their drawworks and engines are usually mounted on trucks or trailers. The load should be borne by hydraulic or. .
Each structure shall be rated for the following applicable loading conditions. The following ratings do not include any allowance for impact. Acceleration, impact, setback, and wind loads will reduce the rated static hook load capacity. Technical specifications are identical to those for derricks: 1. Maximum hook load given the reeving system, 2. F. .
For conventional Mast (Land rig), the below pictures show the erection sequence of rigging up For rigging up the vertical mast, the below pictures show the bootstrap sequence of rigging up.
[pdf] 
Drilling derricks and Rig Masts consist of a steel framework with a square or rectangular cross-section. Their purpose is to support the hoisting equipment and rack the tubulars while tripping pipe. The number of joints in a stand (single-double-triple) that the rig can pull is dependent on the height of the derrick. .
The Drawworks is one of the most important components of the drilling rig (types of drilling rigs). The unit supplies the hoisting power, the. .
The Crown Blockas a drilling rig component is a fixed set of pulleys (called sheaves) located at the top of the derrick or mast, where the drilling line is threaded. The companion blocks to these pulleys are the traveling blocks. By using two sets of blocks in this fashion,. .
The Traveling Blockis a set of sheaves (pulleys) that move up and down in the derrick. The drilling line is threaded (reeved) over the. .
Attached to the bottom of the traveling blocks, the hook is required to hang the swivel and rig kelly(for drilling) and the elevator bales (for tripping pipe and casing).